If you are in one of our active zones, it’s typically 6-8 weeks to get the line built to your house during spring, summer and fall. In the winter, it’s generally 8-12 weeks. Once the box is installed on your house, then we call to schedule your installation in the next 3-4 weeks.
SE Michigan/NW Ohio
Here is the construction schedule:
Substation |
Construction starts |
Installations begin |
Tecumseh |
Oct. 2019 |
Q2 2020 |
Woodstock |
Q1 2020 |
Q3 2020 |
Seneca |
Q3 2020 |
Q4 2020 |
Palmyra |
Q1 2021 |
Q2 2021 |
Ohio |
Q3 2021 |
Q4 2021 |
Am I Eligible for Service?
Not sure if we serve your area or if your area is considered active? Please check your address to see if you are eligible. If you are not in an area that we currently serve, please continue through the steps once you've entered your address. We may come to your area in the future and are using the amount of interest we get in specific places to determine where we'll go next.
Check Your Address for Eligibility
Back to Support